​City of Fontana
Completion Date: 2007
Project Cost: $8 Million     
The Foothill Boulevard street, sewer and storm drain improvement project is located in the City of Fontana, north of Interstate 10 Freeway and East of the Interstate 15 Freeway from Ilex Avenue to Redwood Avenue. Street widening and sidewalk improvements provided for increased vehicular capacity, corridor beautification, a bike lane extension and improved traffic and pedestrian safety. Turnkey design services were provided by TKE for approximately 11,800 linear feet of street widening, sewer and storm drain improvements, a bike lane extension and median improvements. TKE prepared all legal descriptions, right-of-way acquisition plats, temporary construction easement plats and grant and easement deeds for 33 separate parcels, as well as providing construction staking.

Project Services
• Conventional ground design surveying
• Right-of-way documentation preparation
• Plans, specifications and cost estimates
• Temporary construction easement preparation
• Bidding assistance
• Construction staking
• As-built verification

Street Improvements